Asset-Class Studios

Data Centres & Digital Infrastructure Studio

A studio that applies the real-estate toolkit to data centres and digital infrastructure — why they are real estate plus infrastructure, what drives their demand and location, how deals and leases are structured, and how to appraise the capex-intensive investment case.

Advanced
7 modules 31 lessons 7 exercises
Ask about this course

The promise

Apply the real-estate toolkit to data centres - the power position that decides everything, demand, deal structures, sustainability constraints and the exit.

By the end you can

  • Grade a grid connection position rather than accept an indicative date
  • Separate announced, contracted and absorbed demand
  • Read the lease clauses that carry the real risk
  • Quantify the PUE-WUE trade-off and price planning risk
  • Build an investment case with a credible buyer at exit

Curriculum

01

The Data Centre Asset

Real estate plus power, cooling and connectivity; hyperscale vs colocation vs edge; why power (MW), not floor area, is the unit of value.

Real Estate Plus: What a Data Centre Actually IsReading
Power, Cooling and Connectivity: The Three SystemsReading
Hyperscale, Colocation and Edge: Why MW Is the UnitReading
Exercise: Characterise a Site for Data-Centre SuitabilityExercise
Reading a Data Centre Specification SheetReading
The Data Centre Asset: CheckQuiz · pass 70%
02

Demand & Location

Cloud and AI demand drivers; power availability, cost and sustainability; latency, land, fibre and the Gulf/Egypt opportunity.

What Drives Demand: Cloud, then AIReading
Power Availability, Cost and SustainabilityReading
Latency, Land, Fibre and the Gulf/Egypt OpportunityReading
Exercise: Score Two Locations for a RequirementExercise
Sizing Demand: From MW Announced to MW AbsorbedReading
Demand and Location: CheckQuiz · pass 70%
03

The Deal & Lease

Build-to-suit, powered shell and turnkey structures; triple-net leases and hyperscaler covenants; WAULT and income security.

Build-to-Suit, Powered Shell and TurnkeyReading
Triple-Net Leases and Hyperscaler CovenantsReading
WAULT and Income SecurityReading
Exercise: Assess Income Security of a Let Data CentreExercise
The Lease Clauses That Actually MatterReading
The Deal and Lease: CheckQuiz · pass 70%
04

Feasibility, Risk & Value

Capex intensity and the power-cost pass-through; obsolescence and technology risk; building the investment case.

Capex Intensity and the Power-Cost Pass-ThroughReading
Obsolescence and Technology RiskReading
Building the Investment CaseReading
Exercise: Appraise a Data-Centre DevelopmentExercise
Feasibility, Risk and Value: CheckQuiz · pass 70%
05

Power, Grid and Energy Strategy

How a data centre actually gets its power — the grid connection queue, on-site generation, power purchase agreements and tariff structures — and why the energy strategy is usually the binding constraint on the whole project.

The Grid Connection and the QueueReading
On-Site Generation and Power Purchase AgreementsReading
Energy Cost, Tariffs and the Pass-ThroughReading
Exercise: Build a Power StrategyExercise
Power and Energy Strategy: CheckQuiz · pass 70%
06

Sustainability, Water and Regulation

PUE, WUE and what the efficiency metrics actually measure, the cooling and water trade-off that decides siting in hot and arid markets, and the planning, moratorium and community risks that now shape where data centres can be built.

PUE, WUE and What the Metrics Actually MeasureReading
Cooling Technology and the Water Trade-OffReading
Planning, Moratoriums and Community OppositionReading
Exercise: Assess the Sustainability and Consent PositionExercise
Sustainability and Regulation: CheckQuiz · pass 70%
07

Operations, Asset Management and Exit

What owning a data centre actually involves after handover — service level agreements and uptime, expansion and re-tenanting, how the sector is valued, and who buys these assets at exit.

The Operating Model and Service Level AgreementsReading
Asset Management, Expansion and Re-TenantingReading
Valuation and Exit: Who Buys These AssetsReading
Exercise: Write the Investment RecommendationExercise
Operations and Exit: CheckQuiz · pass 70%

Course assessment

Data Centres & Digital Infrastructure Studio — AssessmentPass 70%

Sign in to open lessons and track your progress.

The capstone project

This course ends in a real professional deliverable. Use the brief and the five criteria below to check your own work against the standard a competent professional would be held to.

Your final deliverable

Data Centre Opportunity: Adviser's Recommendation

Check your work against five criteria

  • Method & rigour: The right framework, applied correctly, with the working shown — not just an answer.
  • Data honesty: Every figure is sourced, triangulated, or explicitly flagged “requires local market data”. Nothing is invented.
  • Analysis & judgment: Assumptions are explicit, at least one alternative is weighed, and the key risks are quantified.
  • Recommendation: A clear, decision-useful conclusion a professional could act on — with the conditions that qualify it.
  • Communication: Structured, concise, and client-ready — the argument lands.

When it's ready

Your deliverable is ready when it meets the bar on all five criteria — work a competent professional could put in front of a client or committee.

Revising your work

The capstone is self-directed: you check your own work against the rubric. Where a criterion isn't met yet, revise that part and check it again — as many times as you need.

More in this academy